SAFe - P.I. Planning [Day 1]

sequences : 7

stopwatch

duration : 10h00

Program Increment (PI) Planning is a cadence-based, face-to-face event that serves as the heartbeat of the Agile Release Train (ART), aligning all the teams on the ART to a shared mission and Vision

Sources :
⤴️ © Scaled Agile, Inc.

  1. 1h00

    Business Context

    byBusiness Owner (Executive)

    A Business Owner or senior executive describes the current state of the business, shares the Portfolio Vision, and presents a perspective on how effectively existing solutions are addressing current customer needs.

  2. 1h30

    Product/Solution Vision

    byProduct Managers

    Product Management presents the current vision (typically represented by the next top 10 upcoming features) and highlights any changes from the previous PI planning event, as well as any forthcoming Milestones

  3. 1h00

    Architecture Vision & Development Practices

    bySystem Architect/Engineering

    System Architect/Engineering presents the architecture vision. Also, a senior development manager may introduce Agile-supportive changes to development practices, such as test automation, DevOps, Continuous Integration, and Continuous Deployment, which are being advanced in the upcoming PI.

  4. 1h30

    Planning Context & Lunch

    byRelease Train Engineer (RTE)

    The RTE presents the planning process and expected outcomes.

  5. 3h00

    Team Breakouts #1

    byTeams

    In the breakout, teams estimate their capacity for each Iteration and identify the backlog items they will likely need to realize the features. Each team creates their draft plans, visible to all, iteration by iteration.

  6. 1h00

    Draft Plan Review

    byTeams + Stakeholders

    During the tightly timeboxed draft plan review, teams present key planning outputs, which include capacity and load, draft PI objectives, potential risks, and dependencies. Business Owners, Product Management, and other teams and stakeholders review and provide input.

  7. 1h00

    Management Review & Problem Solving

    byRTE + PM / Management

    It’s likely that the draft plans present challenges such as scope, people and resource constraints, and dependencies. During the problem-solving meeting, management may negotiate scope changes and resolve other problems by agreeing to various planning adjustments. The RTE facilitates and keeps the primary stakeholders together for as long as necessary to make the decisions needed to reach achievable objectives.